Construction Contract
 
- Main contractor
 

Main contract awarded to Larsen & Toubro

 
  • Sub Structure
    • Post tensioned slab

3rd BASEMENT

Completion Date 10-05-06

2nd BASEMENT

Completion Date 17-06-06

1st BASEMENT

Completion Date 28-06-06
  • Super Structure

Ground Floor Level
Completed on 19th Jul 2006
First Floor Level
Completed on 12th Aug 2006
Second Floor Level
Completed on 29th Aug 2006
Third Floor Level
Completed on 7th Sept 2006
Fourth Floor Level
Completed on 16th Sept 2006
Fifth Floor Level
Completed on 29th Sept 2006
Sixth Floor Level
Completed on 4th Oct 2006
Seventh Floor Level
Completed on 11th Oct , 2006
Eight Floor Level
Completed on 17th Oct 2006
Ninth Floor Level
Completed on 28th Oct 2006
Tenth Floor Level
Completed on 5th Nov 2006
Eleventh Floor Level
Completed on 13th Nov 2006
Twelfth Floor Level
Completed on 18th Nov 2006
Thirteenth Floor Level
Completed on 23th Nov 2006
Fourteenth Floor Level
Completed on 28 th Nov 2006
Fifteenth Floor Level
Completed on 5th Dec 2006
Sixteenth Floor Level
Completed on 11th Dec 2006
Seventeenth Floor Level

Completed on17rd Dec 2006

Eighteenth Floor Level
Completed on 21st Dec 2006
Nineteenth Floor Level
Completed on 27th Dec 2006
Twentieth Floor Level
Completed on 6th Jan 2007
Twenty first Floor Level
Completed on 11th Jan 2007
Twenty second Floor Level
Completed on 16th Jan 2007
Twenty third Floor Level
Completed on 25th Jan 2007
Twenty fourth Floor Level
Completed on 01st Feb 2007
Twenty fifth Floor Level
Completed on 06th Feb 2007
Twenty sixth Floor Level
Completed on 12th Feb 2007
Twenty seventh Floor Level
Completed on 17th Feb 2007
Twenty eight Floor Level
Completed on 21st Feb 2007
Twenty nine Floor Level
Completed on 28th Feb 2007
Thirtieth Floor Level
Completed on 5th March 2007
Thirty first Floor Level
Completed on 11th March 2007
Thirty second Floor Level
Completed on 19th March 2007
Thirty third Floor Level
Completed on 26th March 2007

Thirty Fourth Floor Level

Completed on 2nd April 2007

Thirty Fifth Floor Level 

Completed on 9th April 2007

Thirty sixth Floor Level

Completed on 17th April 2007

Thirty Seventh Floor Level

Completed on 23rd April 2007

Thirty Eight Floor Level

Completed on 29th April 2007

Thirty Ninth Floor Level

Completed on 7th May 2007

Roof Floor Level

Completed on 23rd May 2007
   
   
 
  • Finishes
    • The Block Work completed
    • The Plastering works are Completed.
    • The Wall Tiling Works Completed.
    • The Floor Tiling works completed
 
 
  • Nominated Sub Contracts:
    • Mechanical, Electrical and Plumbing: – Contract awarded to M/S Trinity Engineering L.L.C.
      • MEP final Stage Finishing is completed till 38 th Floor.
      • MEP Commissioning has started in 1 st 10 floors.
    • Elevators: - Contracts awarded to Al Yousuf Electronics. Authorized agents for Fujitec Elevators, Japan
      • Lift works have been completed and the lifts are running on slow speed.
    • Aluminum and Glazing:- Letter of nomination issued to Bin Lahej Aluminum
      • The External Aluminium Glazing works are completed.
    • Window Cleaning Equipment:- Letter of nomination issued to DANWAY
      • The rails have been fixed on site
    • Supply and Installation of Doors – Letter of Nomination Issued to Al Khaleej Metal Coat L.L.C
      • Fixing of Doors has been completed.
      • The Selant filing and door alignment is in progress
    • Supply and Installation of False Ceiling Works – DICOTECH
      • False Ceiling Works have been completed till 38 th Floor.

 