| Construction Contract |
| |
| - Main contractor |
| |
|
| |
|
|
|
|
|
|
|
|
3rd BASEMENT 
|
Completion Date 10-05-06 |
2nd BASEMENT 
|
Completion Date 17-06-06 |
1st BASEMENT 
|
Completion Date 28-06-06
|
|
|
Completed on 19th Jul 2006 |
|
Completed on 12th Aug 2006 |
|
Completed on 29th Aug 2006 |
|
Completed on 7th Sept 2006 |
|
Completed on 16th Sept 2006 |
|
Completed on 29th Sept 2006 |
|
Completed on 4th Oct 2006 |
|
Completed on 11th Oct , 2006 |
|
Completed on 17th Oct 2006 |
|
Completed on 28th Oct 2006 |
|
Completed on 5th Nov 2006 |
|
Completed on 13th Nov 2006 |
|
Completed on 18th Nov 2006 |
|
Completed on 23th Nov 2006 |
| |
Completed on 28 th Nov 2006 |
| |
Completed on 5th Dec 2006 |
| |
Completed on 11th Dec 2006 |
Seventeenth Floor Level
|
Completed on17rd Dec 2006 |
Eighteenth Floor Level
|
Completed on 21st Dec 2006 |
Nineteenth Floor Level
|
Completed on 27th Dec 2006 |
|
Twentieth Floor Level
|
Completed on 6th Jan 2007 |
Twenty first Floor Level
|
Completed on 11th Jan 2007 |
Twenty second Floor Level
|
Completed on 16th Jan 2007 |
Twenty third Floor Level
|
Completed on 25th Jan 2007 |
Twenty fourth Floor Level
|
Completed on 01st Feb 2007 |
Twenty fifth Floor Level
|
Completed on 06th Feb 2007 |
Twenty sixth Floor Level
|
Completed on 12th Feb 2007 |
Twenty seventh Floor Level
|
Completed on 17th Feb 2007 |
Twenty eight Floor Level
|
Completed on 21st Feb 2007 |
Twenty nine Floor Level
|
Completed on 28th Feb 2007 |
Thirtieth Floor Level
|
Completed on 5th March 2007 |
Thirty first Floor Level
|
Completed on 11th March 2007 |
Thirty second Floor Level
|
Completed on 19th March 2007 |
Thirty third Floor Level
|
Completed on 26th March 2007 |
Thirty Fourth Floor Level
|
Completed on 2nd April 2007 |
Thirty Fifth Floor Level
|
Completed on 9th April 2007 |
Thirty sixth Floor Level
|
Completed on 17th April 2007 |
Thirty Seventh Floor Level
|
Completed on 23rd April 2007 |
Thirty Eight Floor Level
|
Completed on 29th April 2007 |
Thirty Ninth Floor Level
|
Completed on 7th May 2007 |
Roof Floor Level
|
Completed on 23rd May 2007 |
| |
|
| |
|
| |
|
|
- The Plastering works are Completed.
|
- The Wall Tiling Works Completed.
|
- The Floor Tiling works completed
|
| |
| |
|
- Mechanical, Electrical and Plumbing: – Contract awarded to M/S Trinity Engineering L.L.C.
|
- MEP final Stage Finishing is completed till 38 th Floor.
- MEP Commissioning has started in 1 st 10 floors.
|
- Elevators: - Contracts awarded to Al Yousuf Electronics. Authorized agents for Fujitec Elevators, Japan
|
- Lift works have been completed and the lifts are running on slow speed.
|
- Aluminum and Glazing:- Letter of nomination issued to Bin Lahej Aluminum
|
- The External Aluminium Glazing works are completed.
|
- Window Cleaning Equipment:- Letter of nomination issued to DANWAY
|
- The rails have been fixed on site
|
- Supply and Installation of Doors – Letter of Nomination Issued to Al Khaleej Metal Coat L.L.C
|
- Fixing of Doors has been completed.
- The Selant filing and door alignment is in progress
|
- Supply and Installation of False Ceiling Works – DICOTECH
|
- False Ceiling Works have been completed till 38 th Floor.
|